National Desk: Bangladesh is preparing to connect the first unit of the Rooppur Nuclear Power Plant to the national grid on a trial basis, potentially supplying about 300 megawatts during November. Technical tests and approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) remain prerequisites; no firm start date has been confirmed.
According to a November 15 report by Bangladesh Sangbad Sangstha (BSS), Deputy Project Director Dr Khalequzzaman said pre-synchronisation preparations were under way. Grid synchronisation could occur this week if the remaining work proceeds as planned, followed by close monitoring and testing.
BAERA Chairman Mahmudul Hasan cautioned that it was too early to confirm the date electricity would begin reaching the grid. Regulators would assess the generation and transmission systems before authorising formal supply.
BSS reported that reaching full generation capacity could take another five to six months. A possible 300 MW trial delivery should therefore not be confused with full commercial operation of the unit.
Image: Illustrative stock photograph, not Rooppur.
Source: BSS, November 15, 2026.